SELECTED LAN PROCESS LINE
Lini Ekstrusi Pemisah Silang LAN
Siapkan pemisah silang yang ditentukan sebagai aliran material yang terdefinisi untuk perakitan inti kabel LAN.
02
PROCESS ROUTE
Pastikan profil sesuai dengan konstruksi kabel
Extrude and collect the plastic cross separator used by a specified LAN cable construction. Match the profile tooling, material, cooling and receiving package to the separator drawing and its downstream cabling feed.
This line is relevant when the approved LAN cable drawing requires a cross separator and the factory plans to manufacture that profile. The starting point is the actual cross section, material and tolerance. Tooling, temperature control, cooling and take-up should be reviewed as a connected profile-production route. Its receiving reel must also suit separator feeding at the cabling stage. A separator-production line and the separator feed on the assembly machine are different parts of the factory scope.
Bahan masuk
Senyawa pemisah yang disetujui dan gambar profil
Finished output
Pemisah silang gulungan untuk perakitan inti kabel
Select by
Dimensi profil, material dan paket umpan
Line scope
Dikonfirmasi dari gambar kabel yang disetujui dan input proyek
Profil pemisah berfungsi untuk konstruksi kabel
The cross-section reference shows why the separator belongs in the cable drawing. Specify its profile, dimensions and material, then match its receiving package to the cabling feed arrangement.
Ikuti proses produksi
STAGE 01
Tentukan pemisah
Sertakan gambar profil aktual dan komposisi. Konfirmasi dimensi pemisah dan posisinya di dalam inti kabel sebelum memilih alat ekstrusi.
STAGE 02
Ekstrusi dan dinginkan profil
Coordinate material feeding, profile tooling, temperature control and cooling with the required profile dimensions.
STAGE 03
Collect for the cabling stage
Specify haul-off, length measurement, storage and take-up. The finished separator package must match the selected cabling feed arrangement.
What a well-defined line gives your project
A profile tied to the cable drawing
Use the required separator geometry and orientation as selection inputs. This connects the extrusion tooling to the core that will receive the profile.
A visible material-transfer interface
Specify storage, take-up and cabling pay-off packages together. The separator becomes an identified incoming material for assembly.
A profile-specific working target
Assess output with the selected compound, tooling and cooling arrangement. This creates a production basis for that profile rather than an assumption from the model name.
03
LINE EQUIPMENT
Equipment duties and configuration
Review each module by its function and the project input it needs. Use the documented arrangement as a configuration reference.
Review the separator extrusion arrangement
Connect compound feeding, profile tooling, cooling, haul-off and collection around the selected separator. The receiving package must work with the downstream cabling operation.
Material feeding and project-selected drying
Supply the approved profile compound and identify any material-preparation or drying duty. Confirm which equipment and material responsibilities are included.
Profile extruder and cross-separator tooling
Form the selected cross section with the extruder and profile tooling. Use the actual separator drawing and tolerances to define the tooling duty.
Temperature and line controls
Identifikasi persyaratan suhu dan pengendalian jalur untuk material dan profil yang dipilih. Dokumentasikan dasar kerja yang akan ditinjau selama penerimaan.
Cooling and drying arrangement
Specify the cooling and drying arrangement around the extruded geometry. Review the required water interfaces and handling of the profile.
Agreed profile or dimensional inspection
The reference includes a laser diameter gauge. Check the actual cross-section dimensions and profile tolerances with an agreed inspection method; a diameter reading alone does not establish every dimension of a cross separator.
Haul-off, length counting and separator take-up
The documented downstream route uses a 400 mm double-wheel capstan, a 9 m accumulator with electronic meter counting, and dual-shaft take-up for 400-630 mm reels. Match the collected separator to the cabling feed.
Configuration reference
HK-50 PLC cross-separator reference
- 50 mm main screw, L/D 26:1; documented screw range 10-110 rpm.
- 25 kg dryer/loader, PLC and HMI line control, and separator profile tooling.
- 1.5 m movable warm-water trough plus 8 m fixed cooling; laser diameter gauge.
- 400 mm double-wheel capstan, 9 m accumulator with meter counter, and dual-shaft take-up for 400-630 mm reels.
The reference project lists 120 m/min for separator production. A separate 450 m/min equipment/design figure is not the working guarantee for every cross profile. Confirm the compound, drawing and acceptance point.
Pilih jalur konfigurasi
Pembuatan kabel memerlukan pemisah
Define its cross section, compound, orientation and receiving package. Use those inputs to review the extrusion and cabling-feed scopes.
Separator is sourced externally
The assembly line still needs a defined feed package and handling interface. Confirm that interface even when profile extrusion is outside the equipment order.
Different separator profiles
Provide each proposed profile and material. Review tooling, cooling, changeover and the working basis for each rather than assuming one model covers every geometry.
04
FACTORY INPUTS
Define the line before comparing quotations
Use the same cable, material and receiving-package requirements when comparing configurations. Unknown items can remain questions for the review.
Your selection brief
Profile drawing
Specify the cross shape, dimensions, tolerance and the required orientation within the cable core.
Material and process
Provide the compound specification, cooling requirements and the working output target for that profile.
Receiving and feeding
Define separator reel dimensions, take-up handling and the interface to the cable-assembly pay-off.
Inputs to include
Cross section
Profile drawing, dimensions, tolerance and orientation in the cable core.
Compound
Exact material specification and preparation requirements.
Tooling scope
Profiles to be produced and the corresponding tooling or changeover duties.
Working target
Required output for the defined profile and material.
Receiving reel
Separator package, storage and cabling pay-off dimensions.
Inspection
Profile-measurement method, samples and acceptance records.
05
SUPPLY SCOPE & QUALITY
Agree supply scope and acceptance
Put the selected equipment, plant interfaces and product-specific checks into the written proposal.
ACCEPTANCE CHECKPOINTS
Checks to agree
- Agree profile dimensions and the inspection method for the actual cross section.
- Review cooling and handling against the separator geometry.
- Check the assembled cable construction and its electrical acceptance separately.
SUPPLY BOUNDARY
Cakupan untuk dikonfirmasi
Separator extrusion prepares an upstream material stream. The separator feed at the cabling machine is a separate interface that must also appear in the complete factory proposal.
Define the acceptance sequence
Trial basis
Agree the profile drawing, compound and tooling for the representative separator trial.
Line and product checks
Review dimensions, cooling, handling and the receiving package at the selected operating point.
Records and transfer
Record the profile results and its cabling-feed interface; define assembled-cable electrical acceptance in the full cable project.
06
RELATED ROUTES
Connect the upstream and downstream stages
Review the material and receiving packages on both sides of this line, then compare the complete LAN cable route.
Incoming operation
The incoming material is the approved separator compound for the selected profile tooling.
Next operation
The output separator is stored and fed into the cable-assembly process when required by the drawing.
Interface to confirm
Confirm both profile production and separator feeding in the factory proposal; they are separate equipment interfaces.
07
REFERENCE PRICING
Plan your equipment budget
Review the EXW reference price for the named configuration, then request a quotation against your cable drawing, output target and required supply scope.
HK-50 cross-separator extrusion configuration
USD 27,500
Per reference line
EXW. Taxes excluded.
Confirm your quotation scope
The documented 50 mm separator-profile extrusion arrangement.
Prices are in USD on an EXW basis and exclude taxes. They apply to the named reference configurations. Final price and validity depend on the agreed equipment, tooling, auxiliaries and project requirements.
Confirm the supply boundary and delivery arrangements in the quotation.
08
CUSTOMER FEEDBACK
Good value, with one project team
Feedback from Devang Shah on HONGKAI’s LAN cable equipment and one-stop project service for Channeltech Systems in India.
Devang Shah
Channeltech Systems
India
1 customer review
LAN cable equipment project
Equipment value and project support
HONGKAI’s LAN cable production equipment offers good value for money. The service is good, and the one-stop solution saved time for our project.
English summary of customer feedback.
09
QUESTIONS BEFORE SELECTION
Questions before selecting the line
Clarify configuration choices, material duties and process boundaries before turning a reference arrangement into an equipment order.
This line manufactures the separator profile. The cabling line assembles the twisted pairs and feeds the separator when required by the cable drawing.
The approved cable construction determines whether one is required. Include the material and equipment route for that specific design.
Confirm the working output with the selected compound, profile tooling, cooling and take-up. A maximum or reference figure is not a profile-specific production guarantee.
It identifies the documented PLC-controlled line and 50 mm main screw. The actual profile, material, tooling, cooling and working target still define the selected configuration.
Confirm its profile and compound specification, receiving package and feed arrangement on the assembly machine. The feed interface remains part of the cable-core route.
Send a separate drawing and material specification for each profile. Identify the required tooling, product mix and changeover duties so the configuration review has a defined basis.
10
PROJECT ENQUIRY
Request a line configuration
Lini Ekstrusi Pemisah Silang LAN
Provide the separator cross-section, compound, tolerances, working target and reel drawings. Identify the cabling machine that will receive the separator and whether more than one profile is planned.
Use the review to agree
- The equipment arrangement and selected configuration route.
- Incoming material, receiving package and plant interfaces.
- The working target, supplied instruments and acceptance basis.
Send the information you already have. Mark undecided requirements for discussion rather than guessing a specification.